The federally owned Trans Mountain Corporation said Wednesday it has issued “notice to proceed” directives to construction contractors, mobilizing the workforce it needs to expand the pipeline.
“I am pleased to announce another significant milestone for the Trans Mountain expansion project,” the corporation’s CEO, Ian Anderson, said in release.
“With the first wave of regulatory approvals complete, we are confident that we have a path forward by which the expansion project construction can commence.”
Contractors are expected to begin mobilizing equipment and crews in “select areas” in August and September.
“Construction work will soon begin in communities along the route, including along the right-of-way in Alberta between Edmonton and Edson, and in the Greater Edmonton area,” the corporation said in Wednesday’s release.
“This includes an immediate return to work at Burnaby Terminal and on land at Westridge Marine Terminal. Specific start dates in the remaining construction areas are subject to final regulatory approvals and permits.”
The corporation expects to receive those additional approvals and permits “over the coming months” and, provided that happens, says the expanded pipeline will be in service by mid-2022.
Trans Mountain expects 4,200 workers will be employed along the corridor by late 2019 and says it “remains committed to prioritizing and maximizing Indigenous, local and regional hiring to the greatest extent possible.”
“Clearly this project has been subjected to numerous delays and setbacks over the past several years,” Anderson said.
“With today’s announcement on the commencement of construction, I firmly believe that we are finally able to start delivering the significant national and regional benefits we have always committed to.”